Traffic plan for the Ferry Terminal Turku field area is finalized
The traffic plan for the field area is finalized and will be refined with the traffic simulation to be carried out at the end of the year. Changes will be made to the traffic plan as needed based on received comments and the requirements of other planning areas.
The phasing of the field construction has been preliminarily planned so that the western part will be implemented in the first phase and will be ready when the S1 pier is put into use. In the second phase, the eastern parts of the field, north and south, will be built. The construction schedule of these parts is significantly influenced by the city’s street area construction schedule and the new passenger rail connection coming from the north.