News in the Ferry Terminal Turku project – January 2025
Planning of the west harbour gate area
The general planning of the new gate area of the upcoming Vientikatu will begin in collaboration with Ramboll. The goal is for the new gate zone to be completed at the same time as the terminal is fully operational.
Planning of the field area
The planning work for the port’s field area is underway, with the aim of initiating the contract inquiry for the first construction phase of the field area in spring 2025. In the first phase, the western part of the field area will be built to be ready when the new S1 pier is taken into use. In the subsequent phases, the eastern parts of the field area, north and south, will be built. These construction works, as well as the repair works of the S2 pier, are preliminarily scheduled for 2026–2027.
Construction works of the S1 pier
The construction works of the S1 pier began in November 2024. The piling works of the land area started in December 2024. The piling works of the sea area will begin in February 2025 and will continue until summer 2025.